Which statement describes the Inactive planning approach?

Explanation:
Inactive planning is a passive stance where planning is minimal and the focus is on preserving the current state rather than preparing for what lies ahead. When a manager is satisfied with the outcome, there’s little motivation to plan for future needs, risks, or improvements, which is the essence of this approach. The other behaviors—planning a crisis response, actively seeking changes, and anticipating the future—reflect more proactive or reactive planning, not inactivity. So the statement that the manager is satisfied with the outcome best describes inactive planning.

Inactive planning is a passive stance where planning is minimal and the focus is on preserving the current state rather than preparing for what lies ahead. When a manager is satisfied with the outcome, there’s little motivation to plan for future needs, risks, or improvements, which is the essence of this approach. The other behaviors—planning a crisis response, actively seeking changes, and anticipating the future—reflect more proactive or reactive planning, not inactivity. So the statement that the manager is satisfied with the outcome best describes inactive planning.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy